    丹戎加东(Tanjong Katong)地陷事故调查完成

    2025 年发生的丹戎加东路地陷事故调查已结束。Building and Construction Authority(BCA)、Ministry of Manpower(MOM)及Land Transport Authority(LTA)宣布:

    • 涉事承包商及多名项目负责人被正式起诉。
    • PUBSurbana Jurong收到有条件警告(Conditional Warning)。
    • BCA 表示,其他同类型在建工程经检查后未发现类似结构安全问题,但相关项目须加强风险管理及监测。
    • 影响:
      对于土木工程、深基坑、污水管道、MRT 及地下工程项目,预计 BCA 将继续加强现场监管、设计审查和施工监测。

    • 事件概述

      事件发生在丹戎加东南路附近的一处工地旁,该工地正在建造一个竖井,用于连接三条新的污水管道。施工内容包括使用高压喷射灌浆桩进行土壤加固以及浇筑钢筋混凝土沉箱环。

      2025年7月26日下午5点50分左右,正在施工的竖井部分发生坍塌,导致泥土涌入竖井。几乎在同一时间,丹戎加东南路出现一个塌陷坑,一辆汽车及其司机坠入坑中。司机被工地工人救出,并被送往医院,当时他意识清醒。

    Charges have been brought against seven parties, namely:

    the builder Ohin Construction Co Pte Ltd and its managing director Ong Khiaw Yang Ivan, project director Raajkumar s/o Nadarajan, and project manager Sellappan Saravanakumar;
    the Qualified Persons Kee Chen Siang and Yau Tze Yin; and
    the resident engineer Senthilnathan Mathyalakan.
    The alleged offending conduct include:

    Unauthorised and non-compliant works – Unauthorised building works and road resurfacing were carried out. The works did not comply with approved plans. The works also proceeded without adequate risk assessment and adequate safe work procedure.
    Licensing and supervisory failures – Specialist building works were carried out without the requisite licence. There were failures in the discharge of supervisory duties.
    Testing and monitoring lapses – Mandatory tests that were stipulated under the approved plans were not carried out. An operational video surveillance system was not maintained at the worksite at the time of the incident.
    Failure to notify authorities and false declarations – The relevant authorities were not notified of the road depression that had occurred prior to the sinkhole formation. There were false declarations regarding the appointment of a site supervisor.
    Further, conditional warnings have been administered against two parties (PUB and Surbana Jurong Consultants Pte Ltd) for offences under the Building Control Act.

    Works for this project remain halted till today. For works to resume, the new project parties to be appointed by PUB will have to submit new structural plans, which will be subjected to comprehensive safety assessments and approval by the BCA Commissioner of Building Control.

    被指控的违规行为包括:

    未经授权和不合规的工程——进行了未经授权的建筑工程和道路重铺工程。这些工程不符合已批准的图纸。此外,这些工程在未进行充分的风险评估和制定充分的安全作业程序的情况下进行。

    许可和监管失职——在未获得必要许可证的情况下进行了专业建筑工程。存在监管失职的情况。

    测试和监控疏忽——未进行已批准图纸规定的强制性测试。事发时,施工现场未维护正常运行的视频监控系统。

    未通知有关部门及虚假申报——相关部门未被告知在塌陷坑形成之前已出现的道路下沉情况。此外,在委任现场主管方面存在虚假申报。

    同时,公用事业局(PUB)和盛邦裕廊顾问私人有限公司(Surbana Jurong Consultants Pte Ltd)因违反《建筑管制法》已收到有条件警告。

    该项目工程至今仍处于停工状态。如需复工,公用事业局将委任新的项目方,并须提交新的结构设计方案,该方案将接受全面的安全评估,并由建设局(BCA)建筑管制专员批准。